Integrated Resource Planning

Beginning in the 1980s, public utility commissions throughout the United States began ordering their electric utilities to prepare Integrated Resource Plans (IRP). The goal was to have more involvement by regulatory personal and other interested parties in utility planning, more transparency in utility planning and more warning when major resource additions were likely to be entered into rate base. All plans must evaluate their current supply and demand resources (energy efficiency), consider expected load growth, and find the lowest cost and least risk combination of new supply-side and demand-side resources to meet that growth. 

Each utility must create a new updated plan every two years, file it with the state’s regulatory commission, answer data requests, and receive an acknowledgment order, which has some weight in rate-making but the Commissions always remind utilities that it carries no guarantees. Typically, in the off years of a filed plan, the utility files an official Update. 

The Coalition follows the IRP progress for each of our major utilities because the fate of QFs can be affected by what a utility includes in their plan, such as the year of deficiency.  Most importantly, the inputs for the calculation of avoided cost come directly out of the plan. 

Idaho Power

OREGON DOCKET LC84 - IDAHO POWER’S 2023 INTEGRATED RESOURCE PLAN (IRP)

03/07/2024 - Idaho Power's Reply Comments; filed by Lisa F. Rackner, Jocelyn Pease, and Lisa Nordstrom

02/08/2024 - Staff's Comments, filed by Kim Herb

02/07/2024 - THE RENEWABLE ENERGY COALITION’S OPENING COMMENTS

02/07/2024 - Renewable Northwest's Opening Comments; filed by Katie Chamberlain, Max Greene, and Diane Brandt

OREGON DOCKET LC78 - IDAHO POWER’S 2021 INTEGRATED RESOURCE PLAN (IRP)

12/19/2022 - UM 2211, UM 2210, UM 2209, AR 638, AR 626, PCN 5, and LC 78 - AWEC's Response to Coalition's Request for Intervenor Funding.  Filed by Tyler Pepple

12/14/2022 - STOP B2H Coalition's Request for Clarification re:  Decision on Acknowledgement meeting on 12/6/22; filed by Jim Kreider

12/09/2022 - Dr. Matt Cooper’s 11-29-22 comments; filed by Dr. Matt Cooper

12/09/2022 - Irene Gilbert’s 11-29-22 comments; filed by Irene Gilbert

12/09/2022 - Lois Barry’s 11-28-22 comments; filed by Lois Barry

12/09/2022 - David Mildrexler’s 11-27-22 comments; filed by David Mildrexler

12/02/2022 - Carol Glaser’s 11-28-22 comments; filed by Carol Glaser

12/02/2022 - Susan Geer’s 11-28-22 comments; filed by Susan Geer

12/02/2022 - Peter Barry -- Notice of Filing Please include in the record --in response to Pacific Power

12/02/2022 - Stop B2H Coalition's Response to PacifiCorp's 12/2/22 letter; filed by Jim Kreider

12/02/2022 - PacifiCorp's letter re: discussion at the November 29, 2022, Special Public Meeting; filed by Matthew McVee

11/28/2022 - NOTICE OF SPECIAL PUBLIC MEETING (Decision on Acknowledgement).  Copies served on 11/23/22

11/18/2022 - Coalition's Comments on Staff Report and Recommendations; filed by Ellie Hardwick and Irion A. Sanger

11/18/2022 - Stop B2H Coalition's Response to Staff Comments; filed by Jim Kreider

11/17/2022 - ALJ Sarah Spruce issues Ruling; DISPOSITION:  MEMORANDUM REGARDING SPECIAL PUBLIC MEETINGS.  Copies served on 11/17/22

10/28/2022 - Staff Report for the November 29, 2022 Special Public Meeting (Item No. 1), by Eric Shierman

10/25/2022 - ALJ Sarah Spruce issues Memorandum; DISPOSITION:  MOTION TO MODIFY PROCEDURAL SCHEDULE GRANTED; EXPEDITED CONSIDERATION GRANTED. Copies served on 10/25/22

09/27/2022 - Chief ALJ Nolan Moser issues Memorandum; DISPOSITION: COMMISSION WORKSHOP ON OCTOBER 6, 2022, CANCELED; REMAINING PROCEDURAL SCHEDULE UNCHANGED. Copies served on 9/27/22

09/07/2022 - REC's Final Comments on Idaho Power's IRP

08/16/2022 - Idaho Power Company's Errata to Reply Comments, filed by Lisa Rackner

08/15/2022 - NOTICE OF SPECIAL PUBLIC MEETING AND AGENDA.  Copies served on 8/15/22.

HEARING scheduled 8/18/2022 1:30 PM begin, 8/18/2022 4:00 PM end

07/07/2022 - THE RENEWABLE ENERGY COALITION’S OPENING COMMENTS

04/12/2022 - ALJ Sarah Spruce issues Memorandum; DISPOSITION: PROCEDURAL SCHEDULE UPDATED. Copies served on 4/12/22

04/06/2022 - ALJ Sarah Spruce issues Prehearing Conference Memorandum. Copies served on 4/6/22

03/18/2022 - Idaho Power Company's Notice of Exception Report Under OAR 860-089-0100, filed by Adam Lowney

03/14/2022 - NOTICE OF PROCEDURAL CONFERENCE. Copies served electronically to LC 78 and Electric service lists on 3/14/22, and via U.S. Mail to those without email address on 3/14/22

01/21/2022 - OREGON CITIZENS' UTILITY BOARD (CUB's) Notice of Intervention with contacts of Michael Goetz, Sudeshna Pal, and Oregon CUB Dockets. Filed by Michael Goetz

01/19/2022 - IDAHO POWER's letter re: Boardman to Hemingway Transmission Line Project; filed by Lisa Rackner

01/18/2022 - Renewable Energy Coalition's Petition to Intervene with contacts of John Lowe, Irion Sanger, and Ellie Hardwick. Filed by Ellie Hardwick

OREGON DOCKET LC74 - IDAHO POWER COMPANY 2019 INTEGRATED RESOURCE PLAN (IRP)

08/04/2021 - Idaho Power Company's Valmy Unit 2 Exit Analysis

08/03/2021 - Stop B2H Coalition Application for Rehearing or Reconsideration of Order 21-184

06/04/2021 - Order No. 21-184 signed by Commissioners Megan W. Decker, Letha Tawney, and Mark R. Thompson; Disposition: DISPOSITION: 2019 IRP ACKNOWLEDGED. Copies served 6/4/21

03/24/2021 - Agenda for April 6, 2021 Special Public Hearing

03/19/2021 - STOP B2H's Response to Staff Report 2nd Amend 2019 IRP, filed by Jim

03/19/2021 - Renewable Northwest's Comments on Staff Report, filed by Sashwat Roy, and Max Greene

03/19/2021 - Renewable Energy Coalition's Comments on the Staff Report; filed by Irion A. Sanger

03/19/2021- Idaho Power's Comments on Staff Report for Special Public Meeting April 6, 2021, filed by Lisa Rackner, Shoshana Baird, and Lisa Nordstrom

03/19/2021 - CUB's Comments on Staff Report for Special Public Meeting April 6, 2021, filed by Sudeshna Pal

03/08/2021 - ALJ Christopher J. Allwein issues Memorandum. Copies served on 3/8/21

03/05/2021 - Staff Report for the April 6, 2021 Special Public Meeting (Item No. RA 1), by Nadine Hanhan

02/05/2021 - Idaho Power Company's Final Comments; filed by Lisa F. Rackner, and Shoshana Baird

01/08/2021 - Renewable Energy Coalitions' Final Comments. Filed by Irion Sanger

01/08/2021 - Staff's Final Comments, filed by Nadine Hanhan

01/08/2021 - CUB's final comments. Filed by Sudeshna Pal

01/08/2020 - Renewable Northwest's Final Comments, filed by Sashwat Roy and Max Greene

01/08/2021 - Renewable Energy Coalitions' Final Comments. Filed by Irion Sanger

11/05/2020 - Proposed Schedule

10/8/20 - Idaho Power's Motion to Postpone Prehearing Conference -Expedited Consideration Requested - filed by Lisa F. Rackner

10/07/2020 - Stephanie Andrus email regarding LC74 and Idaho Power Company’s Amended IRP Application

10/02/2020 - IDAHO POWER COMPANY'S AMENDED IRP APPLICATION Lisa F. Rackner and Lisa D. Nordstrom

07/01/2020 - IDAHO POWER'S MOTION TO SUSPEND PROCEDURAL SCHEDULE AND UPDATE REGARDING BOARDMAN TO HEMINGWAY TRANSMISSION LINE PROJECT. Filed by Lisa Rackner

06/15/2020 - ALJ Christopher J. Allwein issues Ruling; DISPOSITION: EXPEDITED MOTION FOR PROCEDURAL SCHEDULE MODIFICATION GRANTED.  Copies served on 6/15/20

06/12/2020 - STAFF's MOTION TO MODIFY PROCEDURAL SCHEDULE [Expedited Consideration Requested]; filed by Stephanie Andrus

05/29/2020 - Idaho Power Company's Amended 2019 Integrated Resource Plan - Replacement Pages.  Filed by Lisa Rackner

04/02/2020 - Gail Carbiener's Opening Comments; filed by Gail Carbiener. Copies served on 4-2-20

04/02/2020 - CUB's Opening Comments; filed by Michael P Goetz

04/02/2020 - Sierra Club Opening Comments: filed by Ana Boyd

04/02/2020 - Renewable Northwest's Opening Comments; filed by Max. Greene

04/02/2020 - STOP B2H COALITION'S Opening Comments filed by Jim Kreider

04/02/2020 - RENEWABLE ENERGY COALITION’S OPENING COMMENTS; filed by Marie P. Barlow and Irion A. Sanger

04/01/2020 - Staff's Opening Comments of Nadine Hanhan.  Filed by Kay Barnes

03/30/2020 - ALJ Alison Lackey issues Ruling PETITION TO INTERVENE GRANTED FOR LIMITED PURPOSES.  Copies served on 3/30/20

03/27/2020 - Idaho Power's Presentation for the March 31, 2020 Special Public Meeting

03/18/2020 - RENEWABLE ENERGY COALITION’S PETITION TO INTERVENE

06/28/2019 - In the Matter of IDAHO POWER COMPANY, 2019 Integrated Resource Plan. Notice of Filing

OREGON DOCKET LC68 - IN THE MATTER OF IDAHO POWER COMPANY 2017 IRP

04/04/2019 - Idaho Power Company's Notice of Exception Report Under OAR 860-089-0100

01/09/2018 - IDAHO POWER IRP UPDATE REPORT. Filed by Dr. Nancy Esteb

7/24/2017 - Oregon Docket LC 68: Prehearing Conference Memorandum and Ruling

PacifiCorp

PACIFICORP 2023 INTEGRATED RESOURCE PLAN (IRP)

04/14/2023 - 2023 IRP Supporting Documents Publicly Posted---4/14/23

12/12/2022 - PacifiCorp’s 2023 Integrated Resource Plan (IRP) Public Input Meeting ----January 12-13, 2023

12/01/2022 - PacifiCorp’s 2023 Integrated Resource Plan (IRP) Public Input Meeting ----December 1-2, 2022

11/26/2022 - PacifiCorp’s 2023 Integrated Resource Plan (IRP) Public Input Meeting ----December 1, 2022

07/21/2022 - PacifiCorp 2023 IRP---July PIM Post-Meeting Materials

PacifiCorp’s 2022 All-Source Request for Proposals

01/24/2023 - Notice to Bidders. Website Questions & Answers Update

01/26/2022 - PacifiCorp 2022AS RFP - Filing Notice

OREGON DOCKET LC77 - PACIFICORP 2021 INTEGRATED RESOURCE PLAN (IRP)

12/27/2022 - NewSun's Comments on PacifiCorp's Waiver Request, filed by Marie Barlow

12/20/2022 - Renewable Northwest's Response to PAC Motion for Waiver, filed by Max Greene

12/20/2022 - Joint Parties Opposition to PacifiCorp's Request for Waiver, filed by Rose Monahan for Sierra Club, Fred Heutte for NWEC, Carra Sahler for GEI, and Michael Goetz for CUB

12/13/2022 - PacifiCorp's Motion for Waiver of IRP Guideline, filed by Carla Scarsella

07/26/2022 - NewSun's Petition for Judicial Review or in the Alternative to Compel Agency Action Pursuant to ORS 183.484 and 183.49 (of Order 22- 178); In the Circuit Court of the State of Oregon For The County of Deschutes (Case No. 22CV24304); filed by Richard G. Lorenz and Casey M. Nokes

08/12/2022 - PacifiCorp’s 2023 Integrated Resource Plan (IRP) Public Input Meeting -September 1-2, 2022

03/21/2022 - NewSun Energy LLC's Motion to File a Reply and Reply, filed by Max M. Yoklic

03/18/2022 - Invenergy LLC's Reply in Support of NIPPC's Request for Certification or, in the Alternative, Request for Clarification, filed by Richard H. Allan

03/16/2022 - ALJ Katharine Mapes issues Ruling; DISPOSITION: MOTION TO STAY AND TOLL PROCEDURAL SCHEDULE OR, IN THE ALTERNATIVE, TO AMEND THE PROCEDURAL SCHEDULE DENIED. Copies served on 3/16/22

03/11/2022 - REC's Reply Comments, filed by Irion A. Sanger

03/11/2022 - CUB's Comments on Staff Report, filed by Sudeshna Pal

03/11/2022 - NWEC Comments on Staff Recommendations, filed by Fred Heutte

03/11/2022 - PacifiCorp's Response to Staff's Final Report, filed by Shelley McCoy

03/11/2022 - Sierra Club's Comments on the Staff Report, filed by Ana Boyd

03/11/2022 - RNW Comments on Staff Report, filed by Sashwat Roy and ax Greene

03/04/2022 - Sierra Club's Reply to PacifiCorp's Response to Sierra Club's Objection to Designation of Certain Information as Confidential. Filed by Rose Monahan

12/06/2021 - Green Energy Institute's (GEI) comments; filed by Carra Sahler

12/06/2021 - Sierra Club's Opening Comments together with Attachments 1-3 (Attachments 1 and 3 are confidential); filed by Gloria D. Smith

12/03/2021 - Renewable Energy Coalition's Opening Comments, filed by Irion Sanger

12/03/2021 - Renewable Northwest's Initial Comments; filed by Sashwat Roy and Max Greene

12/03/2021 - NWEC's Opening Comments, filed by Fred Heutte

12/03/2021 - Swan Lake and Goldendale comments; filed by Michael Rooney

12/03/2021 - CUB's Opening Comments, filed by Sudeshna Pal

12/03/2021 - Staff's Opening Comments, filed by Rose Anderson

10/04/2021 - ALJ Sarah Rowe issues Prehearing Conference Memorandum. Copies served on 10/4/21

10/01/2021 - PacifiCorp's 2021 Integrated Resource Plan (IRP) Public-Input Meeting: October 1, 2021

09/30/2021 - Responses to OPUC Docket LC 77 Staff's Proposed Schedule

09/30/2021 - PacifiCorp's Sensitivity Analysis. Filed by Shelley McCoy

09/29/2021 - OPUC Docket LC 77 Staff's Proposed Schedule

09/24/2021 - REC PacifiCorp 2021 IRP Update Memo

09/22/2021 - PacifiCorp's 2021 Integrated Resource Plan (IRP) Public-Input Meeting: October 1, 2021

09/01/2021 - In the Matter of PACIFICORP, dba PACIFIC POWER, 2021 Integrated Resource Plan. Filed by Shelley McCoy

08/27/2021 - PacifiCorp's 2021 Integrated Resource Plan (IRP) Public-Input Meeting: August 27, 2021

07/30/2021 - PacifiCorp's 2021 Integrated Resource Plan (IRP) Public-Input Meeting: July 30, 2021

02/12/2021 - PacifiCorp's Request for Extension of the 2021 RIP Filing to September 1, 2021. Filed by Etta Lockey

02/08/2021 - PacifiCorp 2021 Integrated Resource Plan (IRP) Upcoming Public Input Meeting (February 10, 2021)

01/29/2021 - Presentation Material for PacifiCorp 2021 IRP Public Input Meeting - January 29 2021

01/12/2021 - Opening Presentation for PAC Upcoming IRP: PACIFICORP CPA DEMAND -SIDE RATES POTENTIAL

07/27/2020 - 2021 IRP Public Input Meeting July 30-31, 2020

07/27/20 - Navigant Private Resource Assessment Presentation

OREGON DOCKET UM2059/UTAH DOCKET 20-035-05 - PACIFICORP APPLICATION FOR APPROVAL OF 2020 ALL-SOURCE REQUEST FOR PROPOSAL

07/30/2020 - 2020 All-Source RFP Update: Potential Bidders and Interested Parties, Bid Submittal Clarifications

07/09/2020 - Bidder’s Workshop

07/07/2020 - Webpage for PacifiCorp’s 2020 All-Source Request for Proposals

06/18/2020 - PacifiCorp's 2020 All-Source RFP - Q&A Update

02/24/2020 - In the Matter of PACIFICORP, dba PACIFIC POWER, Application for Approval of 2020 All-Source Request for Proposal. Filed by Jessica Buno Ralston

OREGON DOCKET LC73 - PACIFICORP 2019 INTEGRATED RESOURCE PLAN (IRP)

12/27/2022 - NewSun's Comments on PGE's Waiver Request, filed by Marie Barlow

11/29/2022 - Renewable NW's Response to PGE's Motion Requesting Waiver of IRP Guideline 2(c).  Filed by Max Greene

11/22/2022 - PGE's Motion Requesting Waiver of Integrated Resource Plan Guideline 2(c).  Filed by Erin Apperson

05/03/2021 - Order No. 21-129, signed by Commissioners Megan W. Decker, Letha Tawney, and Mark R. Thompson; DISPOSITION: STAFF'S RECOMMENDATION ADOPTED WITH GUIDANCE. Copies served on 5/3/21

04/20/2021 - NewSun Supplemental Comments submitted April 20, 2021, filed by Jake Stephens, CEO

04/20/2021 - Issue Matrix for the April 20, 2021 Special Public Meeting

04/12/2021 - Swan Lake and Goldendale Comments to Staff Report, filed by Nathan Sandvig and Michael Rooney

04/12/2021 - PGE Response to Staff Report, filed by Erin Apperson

04/12/2021 - Renewable Energy Coalition's Comments on the Staff Report, filed by Irion A. Sanger

04/12/2021 - CUB's Reply Comments, filed by Sudeshna Pal

04/12/2021 - New Sun Energy Update Comments on Staff Report, filed by Marie P. Barlow

04/12/2021 - Renewable Northwest's Comments on PGE’s IRP Update; filed by Max Greene

04/09/2021 - NOTICE OF SPECIAL PUBLIC MEETING AND AGENDA. Copies served on 4/9/21

03/24/2021 - PGE's Reply Comments submitted by Erin Apperson

03/10/2021 - COALITION's Comments, filed by Irion Sanger

03/10/2021 - Staff's Comments, filed by Max St. Brown

03/10/2021 - Renewable Northwest's Comments, filed by Max Greene

03/10/2021 - NewSun Energy LLC's Comments, filed by Marie P. Barlow

03/10/2021 - NWEC's Comments, filed by Fred Heutte

03/10/2021 - NIPPC's Comments, filed by Irion Sanger

03/10/2021 - CUB's Comments, filed by Sudeshna Pal

03/04/2021 - Swan Lake and Goldendale's Comments, filed by Nathan Sandvig and Michael Rooney

02/17/2021 - RENEWABLE ENERGY COALITION’S SECOND SET OF DATA REQUESTS TO PGE

03/06/2020 - The Renewable Energy Coalition's comments on Staff's Public Meeting Memo.  Filed by Marie P. Barlow and Irion A. Sanger

03/06/2020 - PGE's comments on Staff's Public Meeting Memo.  Filed by Erin Apperson

03/06/2020 - SWAN LAKE's Comments on Staff Report, filed by Sidney Villanueva

03/06/2020 - CUB's Comments on Staff Report, filed by Sudeshna Pal

03/06/2020 - NWEC's Comments on Staff Report, filed by Wendy Gerlitz and Fred Heutte

02/27/2020 - Staff Report for the March 16, 2020 Special Public Meeting, by Caroline Moore

02/05/2020 - NOTICE OF SPECIAL PUBLIC MEETING AND SCHEDULE MODIFICATION.  Copies served on 2/5/20

02/04/2020 - STAFF's Motion to Modify Procedural Schedule [Expedited Consideration Requested], filed by Johanna Riemenschneider

01/17/2020 - PGE's Final Comments, filed by Erin E. Apperson

01/14/2020 - NOTICE OF SPECIAL PUBLIC MEETING AGENDA

12/24/2019 - NOTICE OF SPECIAL PUBLIC MEETING.  Copies served on 12/24/19

12/17/2019 - AWEC's Final Comments, filed by Bradley Mullins

12/17/2019 - Staffs Final Comments, filed by Kay Barnes

12/17/2019 - Renewable Northwest's Final Comments, filed by Silvia Tanner, Max Green, and Natalie McIntire

12/17/2019 - NW Energy Coalition Final Comments, filed by Fred Huette

12/17/2019 - NIPPC's Final Comments, filed by Irion A. Sanger and Marie P. Barlow

12/17/2019 - CUB's Final Comments, filed by Sudeshna Pal and Bob Jenks

12/17/2017 - The Renewable Energy Coalition’s Final Comments

12/16/2019 - Swan Lake's Final Comments, filed by Nathan Sandvig and Erik Steimle.  Copies served on 12/16/19

12/11/2019 - PGE's Errata to 2019 IRP Plan Updated Needs Assessment filed on November 27, 2019 corrects Figure 3 and Table 5.  Filed by Erin Apperson

11/22/2019 - ALJS Sarah Rowe issues Ruling; DISPOSITION: MOTION TO MODIFY PROCEDURAL SCHEDULE GRANTED. Copies served on 11/22/19

11/18/2019 - Staff's Motion to Amend Procedural Schedule

10/24/2019 - Notice of Commission Workshop and Agenda. Copies served on 10/24/19

10/11/2019 - The United States Endowment for Forestry and Communities, Inc. Public Comments on Portland General Electric (PGE) Integrated Resource Plan. Filed by Matt Krumenauer

10/11/2019 - CUB's Opening Comments filed by SudeshnaPal and Bob Jenks. Copies served to service list on 10/11/19

10/11/2019 - AWEC's Opening Comments submitted by Tyler C. Pepple. Copies served to service list on 10/11/19

10/11/2019 - NWEC's Opening Comments submitted by Wendy Gerlitz, Fred Heutte, and Annabel Dayton

10/11/2019 - Renewable Northwest's Opening Comments submitted by Silvia Tanner, Max Greene, Michael H. O'Brien, and Natalie McIntire. Copes served to the service list on 10/11/19

10/11/2019 - Staff's Opening Comments submitted by Kay Barnes. Copies served to the service list on 10/11/19

10/11/2019 - The Renewable Energy Coalition's Opening Comments submitted by Irion A. Sanger and Marie P. Barlow. Copies served to service list on 10/11/19

09/11/2019 - ALJ Sarah Rowe and ALJ Christopher J. Allwein issues Ruling; DISPOSITION: MOTION TO MODIFY PROCEDURAL SCHEDULE GRANTED. Copies served on 9/11/19

06/13/2019 - Notice of Filing-PGE's Objection to Northwest and Intermountain Power Producers Coalition's Request to Designate Henry Tilghman as a Qualified Consultant

06/06/2019 - ALJs Sarah Rowe and Christopher J. Allwein issue Prehearing Conference Memorandum.  Copies served on 6/6/19

05/28/2019 - RENEWABLE ENERGY COALITION (The Coalition) Petition to Intervene with contacts of John Lowe, Marie Barlow, and Nancy Esteb; filed by Marie Barlow

OREGON DOCKET LC70 - PACIFICORP 2019 INTEGRATED RESOURCE PLAN (IRP)

04/17/2023 - Sierra Club's Request to Change the Service List, removing Julian Aries and Ana Boyd, and adding Rose Monahan.  Filed by Rose Monahan

04/14/2023 - PacifiCorp's Compliance Filing per Order No. 20-186. Informational Filing on Customer Preference Agreements in Rocky Mountain Power's Utah Service Territory. Filed by Matthew McVee. Highly confidential to agency folder.  

05/05/2021 - Order No. 21-141 signed by Chief Administrative Law Judge Nolan Moser; DISPOSITION: STAFF'S RECOMMENDATON ADOPTED. Copies served 5/05/2021

04/29/2021 - Staff Report for the May 4, 2021 Public Meeting (Item No. RA3), by Rose Anderson

03/26/2021 - PacifiCorp's Petition for Partial Waiver of OAR 860-027-0400(8), filed by Carla Scarsella

02/11/2021 - PacifiCorp's Presentation for the 2/11/21 Special Public Meeting

04/29/2020 - COALITION's Comments on Staff Report, filed by Marie P. Barlow

04/28/2020 - NOTICE OF SPECIAL PUBLIC MEETING AND AGENDA.  Copies served on 4/28/20

04/17/2020 - Staff Report for the May 7, 2020 Special Public Meeting, by Rose Anderson

03/06/2020 - NOTICE OF SPECIAL PUBLIC MEETING AND AGENDA.  Copies served on 3/6/20

03/04/2020 - STAFF's Final Comments, filed by Rose Anderson

03/04/2020 - COALITION's Final Comments, filed by Marie Barlow

02/13/2020 - PacifiCorp's Presentation for the February 13, 2020 Special Public Meeting

02/10/2020 - Gail Carbiener's Comments, filed by Gail Carbiener

02/05/2020 - PACIFICORP's Reply Comments, filed by Etta Lockey

02/05/2020 - NOTICE OF SPECIAL PUBLIC MEETING AND SCHEDULE MODIFICATION.  Copies served on 2/5/20

01/10/2020 - NIPPC's Comments, filed by Irion Sanger

01/10/2020 - NWEC's Comments, filed by Fred Wendy Gerlitz and Fred Heutte

01/10/2020 - SWAN LAKE NORTH HYDRO's Comments, filed by Nathan Sandvig and Erik Steimle

01/10/2020 - Sierra Club's Comments, filed by Gloria Smith

01/10/2020 - Renewable NW Comments, filed by Max Green and Silvia Tanner

01/10/2020 - CUB's Opening Comments, filed by Sudeshna Pal

01/10/2020 - The Renewable Energy Coalition’s Opening Comments

01/10/2020 - AWEC's Comments, filed by Tyler Pepple

11/22/2019 - VITESSE's Petition to Intervene, with contacts of R. Bryce Dalley and Richard Lorenz. Filed by Richard Lorenz

11/13/2019 - PACIFICORP's IRP Plan Update, filed by Etta Lockey

11/11/2019 - REC's 1st Set of Data Requests to PacifiCorp

10/30/2019 - ALJ Sarah Rowe issues Scheduling Conference Memorandum. Copies served on 10/30/19

07/17/2019 - PacifiCorp's Notice of Extension of Filing Date of its 2019 Integrated Resource Plan, filed by Etta Lockey.

05/17/2019 - SIERRA CLUB's Comments on PacifiCorp Stacked Coal Retirement Analyses, filed by Gloria Smith

05/24/2019 - PacifiCorp's Presentation for the 5/30/19 Special Public Meeting

05/16/2019 - PacifiCorp's Compliance Filing

03/28/2019 - Multnomah County's Comments, filed by Deborah Kafoury

04/05/2019 - PACIFICORP's Compliance per Order No. 18-420, Energy Efficiency Analysis Report.  Filed by Etta Lockey

02/25/19 - Update on the LC 70 process regarding PacifiCorp’s coal analysis

02/06/2019 - PacifiCorp's Notice of Exception under OAR 860-089-0100 (Service List LC 70)

01/08/2018 - SIERRA CLUB's Comments on PacifiCorp Coal Analysis Next Steps.  Filed by Gloria Smith

12/14/2018 - Order No. 18-465 signed by Commissioners Megan W. Decker, Stephen M. Bloom, and Letha Tawney; Disposition: Administrative Law Judge Ruling Certified and Affirmed.  Copies served to LC 67 and LC 70 service lists 12/14/18

12/12/2018 - Staff Report for the December 18, 2018 Special Public Meeting, filed by Rose Anderson

10/15/2018 - SIERRA CLUB'S Comments on PacifiCorp Coal Analysis Methodology.  Filed by Gloria D. Smith

OREGON DOCKET LC67 - IN THE MATTER OF PACIFICORP, DBA PACIFIC POWER'S 2017 IRP. 

07/28/2022 - PacifiCorp's Compliance Filing New Wind and Transmission Projects Quarterly Update, filed by Shelley McCoy

04/29/2021 - PacifiCorp's Compliance Filing per Order No. 18-138, New Wind and Transmission Projects Quarterly Update. Filed by Shelley McCoy

04/27/2021 - LC 62, LC 67 - Sierra Club Comments on PacifiCorp's April 12, 2021 Report. Filed by Rose Monahan

04/12/2021 - LC 62, LC 67 - PacifiCorp's Written Report on DSM IRP Acquisition Goals, Environmental Compliance and Transmission Investments, 2020 Second Update. Filed by Etta Lockey

01/27/2021 - PacifiCorp's Compliance Filing per Order No. 18-138, New Wind and Transmission Projects Quarterly Update. Filed by Michael Wilding

10/21/2020 - PacifiCorp's Compliance Filing per Order No. 18-138, New Wind and Transmission Projects Quarterly Update. Filed by Etta Lockey

09/01/2020 - PacifiCorp's Compliance Filing per Order No. 18-138, New Wind and Transmission Projects Quarterly Update.  Filed by Etta Lockey

05/06/2020 - PacifiCorp's Compliance Filing per Order No. 18-138, New Wind and Transmission Projects Quarterly Update.  Filed by Michael Wilding

03/11/2020 - LC 62, LC 67 - PacifiCorp's Written Report on DSM IRP Acquisition Goals, Environmental Compliance and Transmission Investments - 2019 Second Update Errata.  Filed by Etta Lockey

01/30/2020 - PacifiCorp's Compliance Filing per Order No. 18-138, New Wind and Transmission Projects Quarterly Update.  Filed by Etta Lockey

12/06/2019 - LC 62, LC 67 - PacifiCorp's Compliance to Order Nos. 14-25 and 16-071, Written Report on DSM IRP Acquisition Goals, Environmental Compliance and Transmission Investments - 2019 First Update. Filed by Etta Lockey

01/07/2019 - PACIFICORP's Compliance filing per Order No. 18-138, New Wind and Transmission Projects Quarterly Update.  Filed by Etta Lockey

10/05/2018 - COALITION's Response to Sierra Club's Appeal of ALJ's August 7, 2018 Ruling Re Protective Order, filed by Irion Sanger

8/06/2018 - COALITION's Response to Sierra Club's Motion to Supplement the Record with Letter Requesting PacifiCorp Transparency.  Filed by Irion Sanger

ADDITIONAL UPDATES

10/12/2020 - PacifiCorp Response to Avangrid October 9, 2020 Regarding LGIA Impact on RFP

07/28/2020 - PacifiCorp’s 2020 All-Source RFP Questions and Answers

03/20/2020 - PacifiCorp’s 2020 All-Source Request for Proposals

01/06/2020 - 2019 IRP Action Plan – Cholla Unit 4 Retirement Update

*05/01/2019 - PacifiCorp IRP Update (Please visit Members Only page under Legal Memorandums for confidential summary)

12/11/2018 - PacifiCorp IRP Public Input Meeting December 3-4, 2018. Oregon-Specific Coal Analysis Meeting December 7, 2018

February 20, 2018 - Independent Evaluator’s Final Report on PacifiCorp’s 2017R Request for Proposals (Final Report)

Portland General Electric

PGE Integrated Resource Planning Website

Oregon Docket LC 80 - PGE 2023 INTEGRATED RESOURCE PLAN (IRP) AND CLEAN ENERGY PLAN (CEP)

01/12/2024 - PGE's Comments on Staff's Final Memo, filed by Riley Peck

09/12/2023 - PGE CEP/IRP Report, filed by Elizabeth Graser-Lindsey

07/27/2023 - Renewable Energy Coalition’s Round 1 Comments

07/19/2023 - RENEWABLE ENERGY COALITION’S SECOND SET OF DATA REQUESTS TO PGE

06/02/2023 Modified Protective Order No. 23-193, signed by Christopher J. Allwein, Administrative Law Judge; DISPOSITION:  MOTION FOR MODIFIED PROTECTIVE ORDER GRANTED. Copies served on 6/2/23

06/01/2023 - PGE's Response to Initial Comments, filed by Riley Peck

05/31/2023 - NOTICE OF SPECIAL PUBLIC MEETING: COMMISSIONER WORKSHOP. Copies served on 5-31-23

04/21/2023 - Renewable Energy Coalition's Petition to Intervene with contact of John Lowe, Irion Sanger, and Ellie Hardwick

11/16/2022 - November 16, 2022 IRP Roundtable Meeting - Updated Presentation Attached

11/13/2022 - Change in PGE IRP Roundtable Format and Facilitation

08/15/2022 - REMINDER: August 18, 2022 IRP Roundtable Meeting

PGE 2021 ALL-SOURCE REQUEST FOR PROPOSALS (RFP)

04/28/2021 - In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Application for Approval of an Independent Evaluator for 2021 All-source Request for Proposals. Filed by Erin Apperson

ADDITIONAL UPDATES

06/29/2021 - COMMENT SCHEDULE FOR DOCKET UM 2176: PORTLAND GENERAL ELECTRIC’S APPLICATION FOR WAIVER OF COMPETITIVE BIDDING RULES

02/05/2021 - PGE's IRP Update - Supplemental Filing, filed by Erin Apperson

02/01/2021 - ALJ Sarah Rowe issues Memorandum. Copies served on 2/1/21. Docket Name: PGE 2019 INTEGRATED RESOURCE PLAN (IRP)

01/29/2021 - PGE's Integrated Resource Plan Update, filed by Erin Apperson. This filing includes PGE's Motion for Acknowledgment of IRP Update

01/25/2021 - LC 73--Draft Schedule for PGE's IRP Update Acknowledgment Process

08/03/2020 - PGE 2020 Colstrip Enabling Study

06/15/2020 - Integrated Resource Plan 2021 IRP Public Input Meeting June 18-19, 2020

08/13/2019 - PGE 2019 IRP OPUC Public Hearing Presentation

05/24/2019 - PGE 2019 IRP Pre-Hearing Conference

12/19/2018 - Summary of Portland General Electric IRP Meeting

Puget Sound Electric

PSE received their acknowledgment letter for the 2017 IRP from the Washington UTC on May 7, 2018. 

02/07/2019 - Summary of Puget Sound Electric IRP Meeting

Avista Energy

11/27/18 - Summary of Avista IRP Meeting

NorthWestern Energy

2019 Electricity Supply Resource Procurement Plan, filed August 20, 2019

Washington

The Washington UTC opened a new docket in 2017 to investigate Integrated Resource Planning and related issues, docket UE-161024. There will be another workshop on May 14, and comments are being accepted. REC participated in an earlier workshop that focused on PURPA-related issues. 

Wyoming

Wyoming opened a generic investigation and rulemaking into IRP rules on August 11, 2017